A Simple Change Order Template for Freelancers
A client asks for “one small change.” The request may be reasonable, but it still changes the work you priced. A short change order gives both sides one place to confirm what changed before you begin.
This guide is for independent designers and developers working on fixed-price projects. It is a communication template, not legal advice, an electronic signature, or a payment agreement.
When to send a change order
Send one when a request changes at least one of these:
- the deliverables;
- the time needed to finish;
- the delivery date;
- the project price;
- work that has already been approved.
You do not need a change order for every typo. Use it when a reasonable person could later disagree about whether the work was included.
Copy-and-paste template
Project update: [short name of request]
Original plan [Describe the relevant deliverable in one or two sentences.]
New request [Describe what the client asked to add or change.]
What this adds [List the new pages, states, revisions, integrations, or files.]
Not included [Name adjacent work that is still outside this update.]
Additional fee [Amount and currency]
Timeline impact [Extra working days and the revised delivery date]
Next step Please reply “approved” if you want me to add this work. I will start after [your payment or confirmation condition]. The original plan remains unchanged until then.
Worked example
Imagine a client hired you to design a five-page marketing site. After approving the homepage, they ask for a campaign landing page with a signup form.
Your update could say:
Original plan: Five marketing pages using the approved component set.
New request: Add one campaign landing page and a connected signup form.
What this adds: Desktop and mobile layouts, form states, confirmation state, and developer handoff.
Not included: Email automation, copywriting, paid-ad creative, or analytics setup.
Additional fee: $480 USD.
Timeline impact: Two additional working days; delivery moves from August 14 to August 18.
Next step: Reply “approved” and pay the additional invoice before work begins.
The useful part is not the document format. It is the decision: keep the original plan, swap existing work, or add the new work with a clear fee and date.
Five checks before you send it
- Describe the request in the client’s language, without blame.
- Name the actual deliverables instead of writing “extra changes.”
- State what is excluded so the new scope does not keep expanding.
- Show one exact fee and one revised date.
- Ask for a clear confirmation before beginning.
Keep a copy with the original proposal, messages, and invoice. If your contract requires a particular approval method, use that method.
Make the conversation easier
A change order should make the choice easier, not make the client feel punished for asking. Keep the tone neutral: the request is possible; it simply changes the plan.
Requotely is being designed to turn a client’s extra request into a clear project update with scope, price, and timeline options. Reserve early access if you want to follow the first release.